Progress continues on Lakehead University’s future STEM hubs in downtown Barrie.
The City of Barrie says interior construction at the 24 Maple Ave. site is nearing completion, while work at 5 Ross St. is advancing steadily.
At Maple Avenue, interior construction is reaching completion, with millwork, vestibule framing and window installations in progress. Mechanical and electrical systems are being commissioned, while lab equipment and furniture continue to arrive ahead of the hub’s opening. The city says exterior work should continue through the summer.
Whereas on Ross Street, demolition work is complete and framing for new classroom entrances and interior partitions is nearly finished. Mechanical and electrical rough-ins continue as crews carry out additional installation and coordination work throughout the building.
In April, Mayor Alex Nuttall toured the locations and talked about the progress so far.
“This isn’t just about a university improving the private sector, improving the way the government and education and business work together,” he said. “It’s also about our young people having access to education in an affordable way and one that’s going to put them onto that path of hope and opportunity.”
In late 2024, the City of Barrie and Lakehead University announced plans to establish a STEM hub in the former Barrie Transit Terminal at 24 Maple Ave. This past winter, they officially added a second hub location at 5 Ross St. to their plans.
The Maple Avenue hub will house specialized teaching and research labs focused on robotics, motors, instrumentation, machines and mechatronics. The Ross Street hub will feature flexible classrooms, collaborative learning spaces, student services, social areas and graduate student offices.
The two hubs are slated to open this fall and will accommodate more than 700 students over their first five years.